Planning Schedule
4 Weeks before the move
- Meet with Paragon, and/or Move Consultant to finalize the move schedule.
- Form Moving Supervisory Team to assist in delegation and implementation.
- Finalize floor plan for new office and assign label and placard colors and
department numbers to provide to your mover.
- Prepare Move Communication Packets for your employees, providing the move
schedule and instructions .
- Schedule and prepare agenda for your Employee Move Orientation Meeting.
- Take inventory of all High-Value items in your office and note any
pre-existing damage. Declare all high-value items to your mover in writing.
- Contact your insurance agent to discuss coverage during your move.
- Meet with your MIS Department to discuss special needs for moving IT
equipment. Paragon can also meet with your MIS Department to explain the
Process for moving computers.
3 Weeks before the move
- Conduct your Employee Move Orientation Meeting.
- Distribute Move Communication Packets to your employees.
- Schedule delivery of moving bins - 2 weeks before the move, File and
Computer Crates and Moving Supplies 1 week before the move.
- Explain Purge / Shredding Process and distribute instructions and identify
location of bins throughout the office.
- Assign individuals to be on-site during the move to answer questions and
supervise the process.
- Distribute list of contact names and telephone numbers where contacts can
be reached on the day of the move.
- Contact Building Management at your new location to review policies and
procedures for move-in day.
- Arrange loading dock and elevator reservations as appropriate at the
origin and destination locations.
2 Weeks before the move
- Purge / Shredding Bins delivered.
- Communicate with your staff, encourage a successful purge process.
- Make list of employees who will not be present for the move and assign an
individual to pack and label their work area.
- Assign individuals to pack and label common areas such as the kitchen,
lounge, etc.
- Draft an emergency contact list for vendors such as Elevator Maintenance,
Building Management, Utilities, Telecom, and Moving Company.
1 Week before the move
- Moving bins, crate dollies, labels, and moving supplies delivered and
distributed.
- Provide Placards to your Mover or Move Consultant to post at the
destination site.
- Confirm dock and elevator reservations and origin and destination
locations.
- Contact Building Management to confirm dates and times.
- Conduct a Final Prep Meeting with Supervisory Team, Mover and Move
Consultant. Review the move schedule and address any last minute needs.
- Communicate with your employees throughout the week, making sure the
packing process is going smoothly and answer any questions.
- Confirm the schedule of individuals who will attend the move and their
roles.
- Distribute 2-way radios and cell phones as appropriate for use during the
move.
- Distribute copies of floor plan to your move supervisors.
- Complete a thorough walk-through of your new office space and take
inventory of existing damage to walls, doorjambs and flooring.
- Install Building Protection at new facility (Doorjamb, Wall, and Floor
Protection).
- Designate a Lost and Found area at the destination site.
|